march, 2025

Excavation works are in progress to excavate the pit. Excavation from the overhead beam to the level of the slab -3 levels was completed with the creation of formwork for the curtain wall, the installation of designed reinforcement with anchoring in piles, the installation of reinforcing mesh and the creation of the DOKA system formwork and concreting of the curtain wall.
Installation of steel collars at the designed height in the first zone of securing the foundation pit from HEA profiles on anchor plates with preparation for the installation of steel spacer profiles on the sides of the excavation in the pile zone provided by the sim project.
The installation of steel spacers and the continuation of excavation to the depth of the foundation slab continue.
february, 2025

The entire excavation to the level of the Head Beam has been completed, and the soil removal from the excavation to the designated landfill for this type of work has been carried out.
The complete piling to the required depth has been finished, along with the concreting of the piles.
The complete reinforcement for the Head Beam has been made, and the entire beam has been concreted.
All persons present at the construction site are adhering to all prescribed safety and health measures at work. With improved weather conditions, the conditions are being met to accelerate the progress of the work.
January, 2025

The construction work on the Signature Zvečanska project continued in January 2025
The preparation of the gravel foundation for the drilling rig was completed. The necessary equipment and materials were delivered: drilling rig, reinforcement cages for the piles.
Work began on constructing the pit protection structure – installing bored piles with a diameter of 400 mm around the perimeter of the building. Currently, 50% of the piles have been completed.
December, 2024

Construction work at the Signature Zvečanska project began in December
The demolition of existing buildings on the project has been completed, the area has been cleared, and all construction waste has been sorted and transported to specialized landfills for waste disposal. Additionally, preparatory works have been carried out: the construction site perimeter has been fenced, a temporary workers' settlement has been organized, and temporary power and water supply systems for the construction site have been installed.
Excavation of the foundation pit has begun. The excavation has been completed to the level from which the installation of the protective foundation pit fence will begin — bored pile foundations around the perimeter of the future building.