Construction work at the Signature Zvečanska project began in December
The demolition of existing buildings on the project has been completed, the area has been cleared, and all construction waste has been sorted and transported to specialized landfills for waste disposal. Additionally, preparatory works have been carried out: the construction site perimeter has been fenced, a temporary workers' settlement has been organized, and temporary power and water supply systems for the construction site have been installed. Excavation of the foundation pit has begun. The excavation has been completed to the level from which the installation of the protective foundation pit fence will begin — bored pile foundations around the perimeter of the future building.
January, 2025
The construction work on the Signature Zvečanska project continued in January 2025
The preparation of the gravel foundation for the drilling rig was completed. The necessary equipment and materials were delivered: drilling rig, reinforcement cages for the piles. Work began on constructing the pit protection structure – installing bored piles with a diameter of 400 mm around the perimeter of the building. Currently, 50% of the piles have been completed.
Contact Us
Please leave your details below and we will get back to you